6.1 Project Maturity Score and Benchmark

Maturity Score

Attributes

Schedule

Cost

Requirement

Technical
Understanding

Technical
Difficulty

Commercial

Operations and
Support

Total

Project Stage

Benchmark

10

9

10

10

10

9

9

67

Service Release

Project Status

10

9

10

10

10

8

10

67

Explanation

Commercial: Contractor is delivering as scheduled and contracted.

Operations and Support: Operating system not applicable tothis refurbishment project.

2009-10 DMO MPR Status - - - -