Project Data Summary Sheet 208
Project Name | BUSHMASTER PROTECTED MOBILITY VEHICLE |
|
Project Number | LAND 116 Phase 3 | |
Capability Type | Replacement | |
Service | Australian Army and Royal Australian Air Force | |
Government 1st Pass Approval | N/A | |
Government 2nd Pass Approval | Nov 98 | |
Total Approved Budget (Current) | $929.8m | |
2010-11 Budget | $109.0m | |
Project Stage | Acceptance Testing | |
Complexity | ACAT II |
___________________________________________________________________________________________
208 Notice to reader
Future dates, Sections; 1.3 (Major Challenges), 4.1 (Measures of Materiel Capability Performance), 5.1 (Major Project Risks) and 5.2 (Major Project Issues) are out of scope for the ANAO's review of this Project Data Summary Sheet. Information on the scope of the review is provided in the Auditor-General's Independent Review Report at p.175. |