2.2 Project Expenditure History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.2 Project Expenditure History

Prior to Jul 10

475.3

Thales Australia
(Prime Contract)

7.5

Thales Australia
(SOTASip)

85.5

Other

4

FY to Jun 11

568.3

76.7

Thales Australia
(Prime Contract)

20.6

Thales Australia
(SOTASip)

Jun 11

Total Expenditure

18.3

Other

5

115.6

Jun 11

Remaining Budget

683.9

245.9

Notes

1

Additional Protected Mobility Vehicles for Enhanced Land Force requirements.

2

Additional Protected Mobility Vehicles for Overlander requirements.

3

Up until July 2010, indexation was applied to project budgets on a periodic basis. The cumulative impact of this approach was $118.9m. In addition to this amount, the impact on the project budget as a result of out-turning was a further $5.7m having been applied to the remaining life of the project.

4

Other expenditure comprises: ILS deliverables ($33.5m), facilities ($6.3m), PSPs ($0.1m), project management and operating expenses ($13.1m), Automatic Fire Suppression Kits (AFSS) ($4.5m) ancillary equipment ($19.6m), support test equipment ($0.1m), system engineering ($5.6m), test and evaluation ($1.1m) and travel ($0.7m).

5

Other expenditure comprises: ILS deliverables ($2.6m), AFSS ($4.8m), SOTAS headsets ($5.2m), PSP ($0.2m), project management and operating expenses ($0.6m), ECA ($4.0m) and Facilities ($0.8m).