Estimate | Actual $m | Variance | Variance Factor | Explanation |
|
| The Year to Date variance of $6.6m is a result of additional price variation claims $0.7m, early delivery of some ECA design elements $1.3m, early completion of facilities in Tamworth $0.8m, early SOTASip deliveries $1.2m, early vehicle delivery milestones $1.8m, early delivery of S&TE $0.7m and $0.1m in other costs. | ||
| Overseas Industry | |||
| Local Industry | |||
6.6 | Brought Forward | |||
| Cost Savings | |||
| FOREX Variation | |||
| Commonwealth Delays | |||
109.0 | 115.6 | 6.6 | Total Variance | |