Test and | Major System / Platform Variant | Original | Current | Achieved | Variance | Notes | ||
System | Troop Vehicle | Jun 04 |
| Dec 04 | 6 |
| ||
Command Vehicle | Sep 04 |
| Mar 06 | 18 |
| |||
Assault Pioneer Vehicle | Oct 04 |
| Dec 06 | 26 |
| |||
Mortar Vehicle | Apr 06 |
| May 07 | 13 |
| |||
Direct Fire Weapon Vehicle A | Apr 06 |
| Apr 07 | 12 |
| |||
Ambulance Vehicle | Aug 07 |
| Feb 08 | 6 |
| |||
Air Defence Vehicle | Sep 11 | Sep 11 | Sep 11 | 0 |
| |||
Acceptance | All PP1 vehicles except | Jun 06 |
| Jun 07 | 13 |
| ||
PP1 - Ambulance | Jul 07 |
| May 08 | 10 |
| |||
Troop Vehicle | May 06 |
| Jun 09 | 37 | 1 | |||
Command Vehicle | Jul 06 |
| Jun 09 | 35 |
| |||
Assault Pioneer Vehicle | Jan 07 |
| Jun 09 | 29 |
| |||
Mortar Vehicle | May 07 |
| Jun 09 | 25 |
| |||
Direct Fire Weapon Vehicle | Mar 07 |
| Jun 09 | 27 |
| |||
Ambulance Vehicle | Jul 07 |
| Jun 09 | 23 |
| |||
Air Defence Vehicle | Apr 12 | Apr 12 | Apr 12 | 0 |
| |||
Notes | ||||||||
| Additional reviews and testing requirements impacted the ability of Thales to conduct Production Acceptance Testing and Evaluation in the original timeframe. The situation was also impacted by the priority to support vehicles deployed on operations. Technical issues that resulted in design changes impacted on the ability to finalise Production and Acceptance Testing and Evaluation. | |||||||