3.2 Test and Evaluation Progress

Test and
Evaluation

Major System / Platform Variant

Original
Planned

Current
Planned

Achieved
/Forecast

Variance
(Months)

Notes

System
Integration

Troop Vehicle

Jun 04

 

Dec 04

6

 

Command Vehicle

Sep 04

 

Mar 06

18

 

Assault Pioneer Vehicle

Oct 04

 

Dec 06

26

 

Mortar Vehicle

Apr 06

 

May 07

13

 

Direct Fire Weapon Vehicle A

Apr 06

 

Apr 07

12

 

Ambulance Vehicle

Aug 07

 

Feb 08

6

 

Air Defence Vehicle

Sep 11

Sep 11

Sep 11

0

 

Acceptance

All PP1 vehicles except 
Ambulance  

Jun 06

 

Jun 07

13

 

PP1 - Ambulance  

Jul 07

 

May 08

10

 

Troop Vehicle

May 06

 

Jun 09

37

1

Command Vehicle

Jul 06

 

Jun 09

35

 

Assault Pioneer Vehicle

Jan 07

 

Jun 09

29

 

Mortar Vehicle

May 07

 

Jun 09

25

 

Direct Fire Weapon Vehicle

Mar 07

 

Jun 09

27

 

Ambulance Vehicle

Jul 07

 

Jun 09

23

 

Air Defence Vehicle

Apr 12

Apr 12

Apr 12

0

 

Notes



1

Additional reviews and testing requirements impacted the ability of Thales to conduct Production Acceptance Testing and Evaluation in the original timeframe.  The situation was also impacted by the priority to support vehicles deployed on operations. 

Technical issues that resulted in design changes impacted on the ability to finalise Production and Acceptance Testing and Evaluation.