3.1  Design Review Progress 

Review

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Design

WGS 6 and WGS Constellation

N/A

N/A

N/A

 

1

Mission System Review

Interim Anchoring Mission System Review

Dec 08

N/A

Nov 09

11

2

Notes

1

The MOU construct does not provide the project with insight into the design review process or design data. A Monthly Status Report is provided to the Commonwealth detailing only summary high level progress status.

2

The Interim Anchoring Mission System Review (MSR) delay was attributed to the unfamiliarity of the contractor with Defence contract requirements in relation to documentation and process. Through a contracted requirement, the Contractor experienced difficulties in meeting the quality requirements of the contract resulting in a requirement for re-work to be performed by the contractor. MSR was essentially a combined Preliminary Design Review, System Requirement Review and Critical Design Review that was expected to span three days.