Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
System Design | N/A | N/A | N/A |
| 1 | ||
Mission System Review | Interim Anchoring Mission System Review | Dec 08 | N/A | Nov 09 | 11 | 2 | |
Notes | |||||||
1 | The MOU construct does not provide the project with insight into the design review process or design data. A Monthly Status Report is provided to the Commonwealth detailing only summary high level progress status. | ||||||
2 | The Interim Anchoring Mission System Review (MSR) delay was attributed to the unfamiliarity of the contractor with Defence contract requirements in relation to documentation and process. Through a contracted requirement, the Contractor experienced difficulties in meeting the quality requirements of the contract resulting in a requirement for re-work to be performed by the contractor. MSR was essentially a combined Preliminary Design Review, System Requirement Review and Critical Design Review that was expected to span three days. | ||||||