2.1  Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.1  Project Budget History

 

 

 

 

 

Jul 04

Original Approved

552.6

 

552.6

 

 

Aug 05

Real Variation - Budgetary Adjustments

(2.1)

 

(2.1)

 

 

 

1

Jun 11

Price Indexation

 

 

127.9

 

2

Jun 11

Exchange Variation

 

 

(66.4)

 

 

Jun 11

Total Budget

550.5

 

612.0