Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
System Requirements | GMLS Mk-13 | Oct 05 | N/A | Oct 05 | 0 |
| |
Dec 05 | N/A | Dec 05 | 0 |
| |||
Mk-92 Fire Control System Solid State CWI | Oct 05 | N/A | Oct 06 | 12 | 1 | ||
Feb 09 | N/A | Feb 09 | 0 |
| |||
Weapons Control System | Oct 07 | N/A | Oct 07 | 0 |
| ||
Preliminary Design | GMLS Mk-13 | N/A | N/A | N/A | 0 |
| |
Sep 07 | N/A | Sep 07 | 0 |
| |||
Mk-92 Fire Control System Solid State CWI | Oct 07 | N/A | Sep 07 | (1) |
| ||
Jun 10 | N/A | Feb 10 | (4) |
| |||
Weapons Control System -Stage 1: HAW | Mar 08 | N/A | Apr 08 | 1 | 2 | ||
Weapons Control System -Stage 2: MCG | Jan 09 | N/A | Feb 09 | 1 | 2 | ||
Critical Design | GMLS Mk-13 | Oct 07 | N/A | Nov 06 | (11) |
| |
Jan 08 | N/A | Jan 08 | 0 |
| |||
Mk-92 Fire Control System Solid State CWI | Jan 08 | N/A | Jan 08 | 0 |
| ||
Jun 10 | N/A | Feb 10 | (4) |
| |||
Weapons Control System - Stage 1: HAW | Aug 08 | N/A | Aug 08 | 0 |
| ||
Weapons Control System - Stage 2: MCG | Jul 09 | N/A | Jul 09 | 0 |
| ||
Notes | |||||||
1 | Delay due to mutually agreeing considerations with respect to Limitation of Liability and Intellectual Property. | ||||||
2 | Delay attributable to consolidation of travel to US for multiple events including this review. | ||||||