3.3  Progress Towards Materiel Release and Operational Capability Milestones

Item

Original Planned

Achieved /Forecast

Variance (Months)

Variance Explanation / Implications

Initial Materiel Release (IMR)

N/A

Dec 09

0

 

Initial Operational Capability (IOC)

Aug 10

Aug 10

0

 

Final Materiel Release (FMR)

Sep 12

Sep 12

0

 

Final Operational Capability (FOC)

Dec 12

Dec 12

0

 

Schedule Status as at 30 Jun 11