5.1  Major Project Risks

Identified Risks (risk identified by standard project risk management processes)

Description

Remedial Action

There is a chance that the installation and test program, necessary to deliver the SM2 capability to meet the In-Service Dates, will be affected by the unavailability of Upgraded FFGs, due to their Fleet Activity Schedule (now Force Generation Plan).

The FFG SPO is working to establish alternative strategies for installation outside scheduled maintenance periods (if possible).

There is a chance that the SM-2 test program will be affected by the non availability of Target/Range services to conduct firing within Australia leading to a delay to schedule and increased costs.

The FFG SPO is engaging the RAN operators and regulators to provide indigenous Test & Evaluation options.

Emergent Risks (risk not previously identified but has emerged during 2010-11)

Description

Remedial Action

N/A

N/A