Identified Risks (risk identified by standard project risk management processes) | |
Description | Remedial Action |
There is a chance that the installation and test program, necessary to deliver the SM2 capability to meet the In-Service Dates, will be affected by the unavailability of Upgraded FFGs, due to their Fleet Activity Schedule (now Force Generation Plan). | The FFG SPO is working to establish alternative strategies for installation outside scheduled maintenance periods (if possible). |
There is a chance that the SM-2 test program will be affected by the non availability of Target/Range services to conduct firing within Australia leading to a delay to schedule and increased costs. | The FFG SPO is engaging the RAN operators and regulators to provide indigenous Test & Evaluation options. |
Emergent Risks (risk not previously identified but has emerged during 2010-11) | |
Description | Remedial Action |
N/A | N/A |