Maturity Score | Attributes | Total | |||||||
Schedule | Cost | Requirement | Technical Understand | Technical Difficulty | Commercial | Operations and Support | |||
Project Stage | Benchmark | 8 | 8 | 8 | 8 | 9 | 8 | 8 | 57 |
Acceptance Testing | Project Status | 8 | 9 | 9 | 7 | 9 | 8 | 7 | 57 |
Explanation | • Cost: Contingency (97% of the total provision available to the project) remains. A Real Cost Decrease via the Approved Major Capital Investment Program 2011-12 Portfolio Budget Statements has been proposed. • Requirement: HMAS Sydney has successfully completed the Stage 2 Mid-Course Guidance lead-ship Acceptance Test live fire events (June 2011). • Technical Understanding: Knowledge needs to operate and support the solution understood. No major impediments to acquiring and transferring this knowledge to the RAN. • Operations and Support: The support systems have been defined and procurement of long-lead support elements progressed. | ||||||||
| |||||||||