3.2  Contractor Test and Evaluation Progress

T&E

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Integration

Rotor Brake

Nov 11

- Feb

14

 

Nov 11 - Feb 14

 

2

Acceptance

CH-47F Chinook helicopter

Mar14 - Nov 15

 

Mar 14 - Nov 15

 

1

Rotor Brake

Apr 14

 

Apr 14

 

2

Notes

1

CH-47F Chinook helicopter acceptance dates are currently estimates only as US Army has yet to sign the production contract for ADF aircraft with Boeing.

2

Rotor brake acceptance dates are currently estimates only as US Army has yet to sign the contract for rotor brake integration with Boeing.