6.1  Project Maturity Score and Benchmark

Maturity Score

Attributes

 

Schedule

Cost

Requirement

Technical Understand

Technical Difficulty

Commercial

Operations and Support

Total

Project Stage

Benchmark

6

6

6

6

6

6

6

42

Enter Contract

Project Status

6

6

6

6

7

6

7

44

Explanation

•  Technical Difficulty: All intended modifications to baseline US Army specification CH-47F Chinook are mature designs and are ready for integration.

•  Operations and Support: Support systems are being procured or remain extant from CH-47D.

2010-11 DMO MPR Status - - - -