Date | Description | Base Date $m | Current $m | Contractor | Notes | ||
2.2 Project Expenditure History |
|
|
|
|
| ||
Prior to Jul 10 |
| 374.5 | 428.3 |
|
| ||
|
| 15.3 | 15.3 |
| BAE | 9 | |
|
| 35.3 | 35.3 |
| Other | 10 | |
|
| 425.1 |
| 478.9 |
|
| |
FY to Jun 11 |
| 3.1 | 4.4 |
|
| ||
|
| 0 | 0 |
| BAE |
| |
|
| 1.4 | 1.4 |
| Other | 11 | |
|
| 4.5 |
| 5.8 |
|
| |
Jun 11 | Total Expenditure | 429.6 |
| 484.7 |
|
| |
|
|
|
|
|
|
| |
Jun 11 | Remaining Budget | 45.2 |
| 52.5 |
|
| |
|
|
|
|
|
|
| |
Notes | |||||||
1 | Real adjustment due to incorrect currency mix used at time of approval. | ||||||
2 | Administrative Savings harvest. | ||||||
3 | Transfer to Joint Materiel Agency for supply of medical allowance list. | ||||||
4 | Joint Ammunition Logistic Organisation for Typhoon (gun) 22mm rounds. | ||||||
5 | Increased scope for the number of Patrol Boats from 12 to 14. | ||||||
6 | Skilling Australia's Defence Industry harvest and transfer to DSG for office fit out in Darwin. | ||||||
7 | Transfer to DSG for upgrades of wharf facilities at Darwin and Cairns. | ||||||
8 | Up until July 2010, indexation was applied to project budgets on a periodic basis. The cumulative impact of this approach was $72.9m. In addition to this amount, the impact on the project budget as a result of out-turning was a further $1.6m having been applied to the remaining life of the project. | ||||||
9 | The BAE contract is a fixed price contract which does not contain indexation or foreign exchange and therefore base date dollar value is the same as current dollar value. | ||||||
10 | Other expenditure comprises: Legal Services $1.3m, Purchase of Rafael Typhoon Cannons $5.3m, Purchase of Cryptographic equipment $2.4m, Consultant Activities $7.1m, Fuel Settlement Deed $1.4m and other operating and capital expenditure not attributable to the aforementioned top two contracts. | ||||||
11 | Other expenditure comprises: DMS supplies in support of OR, $0.7m, Software upgrades\installations, $0.2m, Site Project Management Services for four rectification periods, $0.3m, generator hire in support of OR activities, $0.1m and $0.2m of other operating and capital expenditure not attributable to the aforementioned top two contracts. | ||||||