Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
Acceptance | ACPB 01 (HMAS ARMIDALE) | May 05 |
| Jun 05 | 1 | 1 | |
ACPB 02 (HMAS LARRAKIA) | Oct 05 |
| Nov 05 | 1 | 1 | ||
ACPB 03 (HMAS BATHURST) | Nov 05 |
| Dec 05 | 1 | 1 | ||
ACPB 04 (HMAS ALBANY) | Mar 06 |
| Apr 06 | 1 | 1 | ||
ACPB 05 (HMAS PIRIE) | Mar 06 |
| Apr 06 | 1 | 1 | ||
ACPB 06 (HMAS MAITLAND) | Jun 06 |
| Jun 06 | 0 |
| ||
ACPB 07 (HMAS ARARAT) | Jul 06 |
| Jul 06 | 0 |
| ||
ACPB 08 (HMAS BROOME) | Oct 06 |
| Oct 06 | 0 |
| ||
ACPB 09 (HMAS BUNDABERG) | Nov 06 |
| Nov 06 | 0 |
| ||
ACPB 10 (HMAS WOLLONGONG) | Mar 07 |
| Apr 07 | 1 | 2 | ||
ACPB 11 (HMAS CHILDERS) | Mar 07 |
| May 07 | 2 | 2 | ||
ACPB 12 (HMAS LAUNCESTON) | Jun 07 |
| Jul 07 | 1 | 2 | ||
ACPB 13 (HMAS MARYBOROUGH) | Sep 07 |
| Sep 07 | 0 |
| ||
ACPB 14 (HMAS GLENELG) | Nov 07 |
| Nov 07 | 0 |
| ||
Notes | |||||||
1 | Boats 1-5 delayed due to contractor labour shortages - permissible delays. | ||||||
2 | Boat 10-12 delayed due to configuration changes and change to delivery location - permissible delays, plus defect rectifications by the contractor. | ||||||