6.1 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage

Benchmark

10

9

10

10

10

9

9

67

Service Release

Project Status

10

9

10

10

9

8

9

65

Explanation

•  Technical Difficulty: The capability has been released for operational use but FOC has not yet been achieved and some elements of contract delivery remain outstanding.

•  Commercial: Some contracted requirements against acquisition contract remain outstanding and performance against the MAA and MSA is broadly satisfactory.

2009-10 DMO MPR Status . . . .

2010-11 DMO MPR Status . . . .