Maturity Score | Attributes | Total | ||||||||
Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | ||||
Project Stage | Benchmark | 10 | 9 | 10 | 10 | 10 | 9 | 9 | 67 | |
Service Release | Project Status | 10 | 9 | 10 | 10 | 9 | 8 | 9 | 65 | |
Explanation | • Technical Difficulty: The capability has been released for operational use but FOC has not yet been achieved and some elements of contract delivery remain outstanding. • Commercial: Some contracted requirements against acquisition contract remain outstanding and performance against the MAA and MSA is broadly satisfactory. | |||||||||
| ||||||||||