3.2 Contractor Test and Evaluation Progress

Test & Evaluation

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

Test Readiness Review

HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Phased Array Radar System/Navigation Radar System - Harbour Phase)

Dec 08

Aug 10

Aug 10

20

1

Acceptance (Initial Operational Capability)

HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Navigation Radar System)

Dec 09

Jul 11

Jul 11

19

1

Notes

1

Variance in both the test readiness review and acceptance of the first upgraded ASMD ship is directly related to the change of acquisition strategy and movement from an eight ship program to a single ship program.