2.1 Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.1 Project Budget History

 

 

 

 

 

Sep 02

Original Approved

455.3

 

455.3

 

 

May 03

Real Variation - Transfers

(0.9)

(0.9)

 

 

1

Aug 04

Real Variation – Budgetary Adjustments

(0.8)

(0.8)

 

 

2

 

 

(1.7)

 

(1.7)

 

3

Jun 11

Price Indexation

 

 

56.5

 

 

Jun 11

Exchange Variation

 

 

(59.7)

 

 

Jun 11

Total Budget

453.6

 

450.4