Identified Risks (risk identified by standard project risk management processes) | |
Description | Remedial Action |
There is a possibility that the replacement combat system installation schedule will be affected by on-going changes to the FCD schedule and boat availability, leading to schedule extensions and significant cost increases to be borne by the project. | This risk is being treated by: • Monitoring the impact of a revised Usage Upkeep cycle. • Establishing project prolongation costs. • Assigning contingency funding to the last boat installation. • Monitoring remaining project funds and budget spend. |
There is a possibility that completion of Category 3 and 4 Testing of future system integration and boat installations will be affected by a shortage of skilled personnel leading to an impact on schedule. | • This risk has been retired. |
Emergent Risks (risk not previously identified but has emerged during 2010-11) | |
Description | Remedial Action |
N/A | N/A |