5.2 Major Project Issues

Description

Remedial Action

Uncertainty in the submarine docking cycle and the availability of submarines has impacted the installation schedule.

•  This risk has been reduced as a result of the stabilisation of the COLLINS Integrated Master Schedule (IMS) in April 2010, which has been accepted by all relevant parties.