Test and Evaluation | Major System / Platform Variant | Original Planned | Current Planned | Achieved/Forecast | Variance (Months) | Notes | |
Harbour Acceptance Tests | Weapon Handling and Discharge Systems Post MK 48 MOD 7 Heavyweight Modification Test HMAS WALLER (First of Class) (CAT 4 Testing] | Jan 07 |
| Apr 07 | 3 | 1 | |
Sea Acceptance Trials | Weapon Discharge System MK 48 MOD 6/7 Heavyweight Torpedo Modification for HMAS WALLER CAT 5 Testing | Oct 07 |
| Dec 07 | 2 | 1 | |
Notes | |||||||
1 | Variance is attributable to the Navy Regulatory Review process and submarine program. | ||||||