6.1 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understanding

Technical Difficulty

Commercial

Operations and Support

Project Stage 

Benchmark

8

8

8

8

9

8

8

57

Acceptance Testing

Project Status

8

8

9

8

8

8

9

58

Explanation

•  Requirement: System integration and testing processes have verified the platform modification requirements and those modifications apply to later Spiral baselines. The APB 4 baseline has also been accepted for IOR. Therefore, the assessment score is marginally ahead of the benchmark score for this particular maturity gate.

•  Technical Difficulty: Spiral 1 software had been granted OR; APB 4 software is still under development and testing. Although there is high confidence that all technical issues will be solved it is appropriate to retain the maturity assessment against this attribute at the lower level at this time.

•  Operations and Support: APBsoftware has been granted Initial OR and has entered into operational testing. Therefore the maturity score is marginally ahead of the benchmark score for this particular maturity grade.

2009-10 DMO MPR Status . . . . .

2010-11 DMO MPR Status . . . . .