Item | Original Planned | Achieved /Forecast | Variance (Months) | Variance Explanation / Implications |
Initial Materiel Release (IMR) | N/A | Jan 11 | N/A |
|
Initial Operational Release Special Forces (DECHAINEUX) | Nov 10 | Sep 12 | 22 | Refer Section 1.2 Current Status: Material Capability Performance. |
Initial Operational Release Torpedo Decoy (DECHAINEUX) | Aug 10 | Dec 11 | 16 | Refer Section 1.2 Current Status: Material Capability Performance. |
Fire Fighting Upgrade (RANKIN) | Oct 13 | Oct 13 | 0 | IOC is linked to successful completion of the Harbour Verification Testing (HVT), where any variance will be caused through movement in the docking maintenance schedule. These dates are based on the IMS of April 2010. |
Sewage System Upgrade (WALLER) | Aug 06 | Oct 07 | 14 | IOC is linked to completion of the FOC Sea Acceptance Testing (SAT). Variance due to changes in docking maintenance schedule since original Materiel Acquisition Agreement (MAA). |
Fast Track | N/A | N/A | N/A | Fast Track initially installed on two submarines and managed under SEA 1446 Phase 1. SEA 1439 Phase 3 is responsible to roll out to remaining four submarines. IOC was the responsibility of SEA 1446 Phase 1. |
Final Materiel Release (FMR) | Oct 22 | Oct 22 |
|
|
Operational Release of Special Forces | Jun 07 | Dec 15 | 102 | The MAA delivery date was for HMA Submarine COLLINS only. HMA Submarine DECHAINEUX implementation through MAA amendment created variance. The delay was further influenced by contractor workforce constraints and the phased delivery of capability enhancements to the Special Forces systems. |
Operational Release of Torpedo Decoy | Jun 14 | Oct 13 | (8) | This modification is largely independent on the constraints of the docking maintenance schedules and can be simultaneously rolled out to platforms. |
Fire Fighting Upgrade (SHEEAN) | Jun 14 | Sep 22 | 99 | Variance due to changes in docking maintenance schedule since original MAA. |
Sewage System Upgrade (FARNCOMB) | Jun 14 | Mar 17 | 33 | Variance due to changes in docking maintenance schedule since original MAA. |
Fast Track (WALLER) | Jul 06 | Nov 07 | 16 | Fast Track initially installed on two submarines and managed under SEA 1446 Phase 1. This project installed the Fast Track upgrades across the remaining four submarines. Variance due to changes in docking maintenance schedule since original MAA. |