2.1 Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.1 Project Budget History

 

 

 

 

 

Feb 09

Original Approved

4.0

 

4.0

 

 

Apr 09

Real Variation - Government Initial 2nd
Pass Approval

269.1

269.1

 

 

 

Apr 10

Real Variation -
Government Final 2nd
Pass Approval

187.8

187.8

 

 

 

 

 

457.0

 

457.0

 

1

 

 

461.0

 

461.0

 

 

Jun 11

Price Indexation

 

 

(3.0)

 

2

Jun 11

Exchange Variation

 

 

(50.7)

 

 

Jun 11

Total Budget

461.0

 

407.2