Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
System Requirements | IS-22 Hosted Payload | Jun 09 | N/A | Jun 09 |
|
| |
Preliminary Design | IS-22 Hosted Payload | Nov 09 | N/A | Oct 09 | (1) |
| |
Oct 10 | N/A | Nov 10 | 1 | 1 | |||
Critical Design | IS-22 Hosted Payload | Sep 10 | N/A | Sep 10 |
|
| |
CSM Critical Design Review | Mar 11 | N/A | Mar 11 |
|
| ||
Notes | |||||||
1 | The review was conducted in October 2010 but Approval by the Project Office did not occur until November 2010 due to a number of issues with requirements traceability that required rectification. | ||||||