Test and Evaluation | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
System Integration | IS-22 Hosted Payload | Nov 10 | N/A | Feb 11 | 3 | 1 | |
Sep 11 | N/A | Sep 11 |
|
| |||
Acceptance | IS-22 Hosted Payload | Jun 12 | N/A | Jun 12 |
|
| |
Jul 12 | N/A | Jul 12 |
|
| |||
Notes | |||||||
1 | Delay to commencement of integration was driven by a number of delays in sub system deliveries including C and Ku antennas (not forming part of this capability) and the UHF antenna. Margin in the schedule has been used to ensure these delays do not delay the Final Acceptance milestone. | ||||||