3.3 Progress Toward Materiel Release and Operational Capability Milestones

Item

Original Planned

Achieved /Forecast

Variance (Months)

Variance Explanation / Implications

Initial Materiel Release (IMR)

Jul 12

Jul 12

 

 

Initial Operational Capability (IOC)

Jul 12

Jul 12

 

On track to meet IOC (coincident with IMR).

Final Materiel Release (FMR)

Sep12

Sep 12

 

 

Final Operational Capability (FOC)

N/A

N/A

 

Not defined in Material Acquisition Agreement, nor in Government second pass documentation.

Schedule Status as at 30 Jun 11