5.2 Major Project Issues

Description

Remedial Action

Network Control System Requirements are currently being refined as the Project improves its understanding of the Military Standards (MILSTDs).

Currently replanning activities to ensure the minimum capability is provided to support IMR with a plan to provide additional capability if required.

Network Control System Delivery currently unclear due to the failure of the tender process to find a successful tenderer.

Currently planning activities for the Project Office to act as the prime systems integrator to provide the required capability.