Maturity Score | Attributes | Total | |||||||
Schedule | Cost | Requirement | Technical Understand | Technical Difficulty | Commercial | Operations and Support | |||
Project Stage | Benchmark | 8 | 7 | 8 | 8 | 8 | 8 | 8 | 55 |
System Integration and Test | Project Status | 8 | 9 | 9 | 7 | 8 | 8 | 7 | 56 |
Explanation | • Cost: IS-22 is essentially an off the shelf product on a firm fixed price contract which means the project is ahead of the benchmark. • Requirement: The essentially off the shelf nature of the IS-22 hosted payload means it is ahead of the bench mark for testing against the requirements. • Technical Understanding and Operations and Support: The project is lagging slightly in Technical Understanding and Operational support primarily due to Defence still developing the Concept of Operations for the capability. | ||||||||
| |||||||||