2.1 Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.1 Project Budget History

 

 

 

 

 

Jan 04

Original Approved
Real Variation - 

449.0

 

449.0

 

 

Aug 04

Budgetary Adjustments
Real Variation - 

(0.1)

(0.1)

 

 

1

Mar 06

Transfers
Real Variation – 

(155.4)

(155.4)

 

 

1

Feb 07

Transfers

(4.4)

(4.4)

 

 

2

 

 

(159.9)

 

(159.9)

 

3

Jun 10

Price Indexation

 

 

101.3

 

4

Jun 10

Exchange Variation

 

 

(0.9)

 

5

Jun 10

Total Budget

289.1

 

389.5

 

6