Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
System Requirements | Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track – Stage 1 (Requirements Review) | Feb 04 |
| Aug 05 | 18 | 1 | |
Mk3E Combat Management System/Fire Control Director – Stage 1 (Functional Review) | Apr 05 |
| Aug 06 | 16 | 1 | ||
Mk3E Combat Management System/Fire Control Director -Stage 1 (System Performance Review) | N/A |
| Nov 06 | N/A |
| ||
ASMD Shore Facilities (HMAS Stirling) | N/A |
| May 06 | N/A |
| ||
Preliminary Design | Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track System - Stage 1 | Nov 05 |
| Aug 07 | 21 | 1 | |
ASMD Shore Facilities (HMAS Stirling) | N/A |
| Nov 06 | 0 |
| ||
Critical Design | Stage 1 Critical Design Review – Part 1 (All except Phased Array Radar in the AFT mast) | Sep 06 |
| May 08 | 20 | 1 | |
Stage 1 Critical Design Review – Part 2 (Remaining components of AFT mast) | N/A |
| Aug 08 | 0 |
| ||
ASMD Shore Facilities (HMAS Stirling) | N/A |
| Jun 07 | 0 |
| ||
Notes | |||||||
1 | Variances indicated are directly linked to: the Government decision to investigate phased array radar technologies in lieu of the requirement for the VSRAD system; and, a realisation of technical risks in Phase 2B which required re-engineering effort to redesign the integration of the phased array radar into the ANZAC platform. | ||||||