| Test and Evaluation | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
| Test Readiness Review | HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track - Sea Phase) | Nov 07 |
| Mar 11 | 40 | 1, 2 | |
| Acceptance | HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track - Sea Phase) | Apr 08 | Jun 11 | Jun 11 | 38 | 1 | |
| Notes | |||||||
| 1 | Variance indicated is directly linked to the Government decision to investigate phased array radar technologies in lieu of the requirement for the VSRAD system and a realisation of technical risks in Phase 2B which required re-engineering effort to redesign the integration of the phased array radar into the ANZAC platform. | ||||||
| 2 | Additional variance of 1 month due to production completion delay of 1 month in lead ship HMAS Perth. | ||||||