3.2 Contractor Test and Evaluation Progress

Test and Evaluation

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

Test Readiness Review

HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track - Sea Phase)

Nov 07

Mar 11

40

1, 2

Acceptance

HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track - Sea Phase)

Apr 08

Jun 11

Jun 11

38

1

Notes

1

Variance indicated is directly linked to the Government decision to investigate phased array radar technologies in lieu of the requirement for the VSRAD system and a realisation of technical risks in Phase 2B which required re-engineering effort to redesign the integration of the phased array radar into the ANZAC platform.

2

Additional variance of 1 month due to production completion delay of 1 month in lead ship HMAS Perth.