6.1 Project Maturity Score and Benchmark

Maturity Score

Attributes

Total

Schedule

Cost

Requirement

Technical Understand

Technical Difficulty

Commercial

Operations and Support

Project Stage

Benchmark

8

8

8

8

9

8

8

57

Acceptance Testing

Project Status

8

8

9

7

9

8

8

57

Explanation

Requirement: Phase 2A is well understood in this area; the upgrade of the Combat Management System to Mk3E and the introduction of the Infra-Red Search and Track System are low risk to the Project and well understood to the customer.

Technical Understanding: With the Infra-Red Search and Track System being new to the RAN (although fielded elsewhere in foreign Navies), there is some risk that the use of this technology will not be fully understood until a period of operation has occurred. Although sea acceptance trials are now successfully complete, Navy operational test and evaluation will not complete until 2013.

2009-10 DMO MPR Status - - - - -

20010-11 DMO MPR Status - - - - -