2.1 Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

2.1 Project Budget History

 

 

 

 

 

Aug 04

Original Approved

14.9

 

14.9

 

1

Dec 05

Government Second Pass Approval

355.3

355.3

 

 

 

 

 

370.2

 

370.2

 

2

Jun 11

Real Cost Decrease

(50.0)

(50.0)

 

 

3

Jun 11

Price Indexation

 

 

62.5

 

 

Jun 11

Exchange Variation

 

 

(39.4)

 

 

Jun 11

Total Budget

320.2

 

343.3