3.2 Contractor Test and Evaluation Progress

Test and Evaluation

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Integration

JASSM System (Weapon integrated into platform) 21X

Jun 09

Feb 11

Feb 11

20

1

 

JASSM System (Weapon integrated into platform) 23X

N/A

Jun 11

Jun 11

0

 

Acceptance

JASSM System (Weapon integrated into platform)

Dec 09

Dec 11

Dec 11

24

2

Notes

1

Data listed is for the F/A-18 21X Build 3.4.1 (JASSM functionality) OFP software which will be used for the IOC. Variance is attributable to the delays associated with correcting software anomalies detected during software development and testing, which required extensive redevelopment and retesting to ensure airworthiness and operational effectiveness.

2

An additional variation of four months between System Integration and Acceptance has been realised due to: delayed delivery of JASSM Test Missiles, Government acceptance of risk associated with Woomera test firings and availability of the Woomera Test Range and support agencies