Maturity Score | Attributes | Total | ||||||||
Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | ||||
Project Stage | Benchmark | 8 | 8 | 8 | 8 | 9 | 8 | 8 | 57 | |
Acceptance Testing | Project Status | 9 | 8 | 9 | 8 | 9 | 8 | 7 | 58 | |
Explanation | • Schedule: The project is currently within the revised schedule which is being formalised following Government endorsement of the Cabinet Submission. • Requirement: Requirements are fully understood and approaching final stages of delivery. • Operations and Support: Operational and Support elements are being procured. System Acceptance cannot be finalised until completion of Operational Test and Evaluation | |||||||||
| ||||||||||