Project Data Summary Sheet221
Project Name | ARTILLERY REPLACEMENT PROJECT |
|
Project Number | LAND 17 Phase 1A | |
Capability Type | Replacement | |
Service | Australian Army | |
Government 1st Pass Approval | Feb 06 | |
Government 2nd Pass Approval | Jul 09 | |
Total Approved Budget (Current) | $326.1m | |
2010-11 Budget | $64.5m | |
Project Stage | System Integration & Test | |
Complexity | ACAT III |
_________________________________________________________________________________________________________________________________________
221 Notice to reader
Future dates, Sections; 1.3 (Major Challenges), 4.1 (Measures of Materiel Capability Performance), 5.1 (Major Project Risks) and 5.2 (Major Project Issues) are out of scope for the ANAO's review of this Project Data Summary Sheet. Information on the scope of the review is provided in the Auditor-General's Independent Review Report at p.175. |