Estimate $m | Actual $m | Variance $m | Variance Factor | Explanation |
|
| 9.3 | Expenditure is $79.3m against latest plan $64.4m. Variance of $14.9m is primarily due to accelerated FMS payments for the Lightweight Towed Howitzers of $9.3m, radio payments of $9.7m brought forward from FY11/12, rescheduling of vehicle integration activities to FY11/12 ($3.0m), and foreign exchange gains ($1.1m). | |
| Overseas Industry | |||
| Local Industry | |||
9.7 | Brought Forward | |||
| Cost Savings | |||
(1.1) | FOREX Variation | |||
(3.0) | Commonwealth Delays | |||
64.4 | 79.3 | 14.9 | Total Variance |