3.1 Design Review Progress

Test and Evaluation

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Requirements

AFATDS

Sep-10

Sep-10

Sep-10

0

 

Preliminary Design Review

N/A

N/A

 

N/A

 

1

Critical Design Review

N/A

N/A

 

N/A

 

2

Notes

1

As both the LW155 and AFATDS are Off The Shelf (OTS) acquisitions, there is no Preliminary Design Review.

2

As both the LW155 and AFATDS are OTS acquisitions there is no Critical Design Review.