3.2 Contractor Test and Evaluation Progress

Review

Major System / Platform Variant

Original Planned

Current Planned

Achieved /Forecast

Variance (Months)

Notes

System Integration

LW155

Sep 11

 

Sep 11

0

1

AFATDS

Sep 11

 

Sep 11

0

2

Acceptance Test and Evaluation

LW155

Sep 11

 

Sep 11

0

3

AFATDS

Sep 11

 

Sep 11

0

3

Notes

1

The project will conduct certification activities in collaboration with relevant Defence agencies, to qualify the LW155 for external and internal airlift and sea transport and compliance with the ADR for road transport.

2

The AFATDS will be tested and certified with multiple combat management systems.

3

Acceptance Test and Evaluation activities are planned from March through to September 2011.