4.1 Measures of Materiel Capability Performance

Pie Chart: Percentage Breakdown of Materiel Capability Performance

Green:

The Land 17 Ph1A project forecasts delivery of the LW155 and AFATDS to the required level of capability in accordance with FMR requirements and associated completion criteria outlined in the MAA.

Amber:

N/A

Red:

The Land 17 Ph1 A project assess the CCF materiel element as Red, noting the capability will be subject to a further program of testing to resolve reliability issues, prior to the US Government agreeing to a production milestone. Government has been advised of the current status. A decision to progress the acquisition of CCF under this phase of Land 17 will be made by December 2012.