Schedule Performance The project remains on schedule with delivery of equipment and training for Initial Materiel Release () planned for June 2011, which will meet Army's requirement to conduct Initial Operating Capability () in July 2011. To date the project has achieved System Design Review (), Preliminary Design Review () and Detailed Design Review () on a number of platforms, was achieved on 14 June 2011. Bushmaster vehicles from the production facility are scheduled for delivery to 7 Brigade by early 2012. Major contract milestones remain on schedule with () planned for April 2013 and Final Operating Capability () in April 2013. |