Contractor | Signature Date | Price (Base) at | Type (Price Basis) | Form of Contract | Notes | ||
Signature $m | 30 Jun 11 $m | ||||||
Elbit Systems Limited | 15 Mar 10 | 176.2 | 176.2 | Variable | 1 | ||
Notes | |||||||
1 | This value represents the Land 75 Phase 3.4 aspect of a contract which covers two other discrete projects. Total contract value is $275.7m, this includes both Acquisition and Sustainment. | ||||||
Contractor | Quantities as at |
| Scope |
| Notes | ||
Signature | 30 Jun 11 | ||||||
Elbit Systems Ltd | Various | Various | Delivery of BMS installations or installation kits for: - Mack Truck: 131 - Unimog Truck: 225 - Bushranger PMV: 193 - M113 APC: 115 - G-Wagons: 388 |
| |||
Major equipment received and quantities to 30 Jun 11 | |||||||
Most Critical/Detailed Design Reviews have been completed. | |||||||