Review | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
System Requirements | System Design Review - BMS | May 10 | N/A | Aug 10 | 3 | 1 | |
Preliminary Design | Group 1 - Various Vehicles | Sep 10 | N/A | Sep 10 | 0 |
| |
Aug 10 | N/A | Sep 10 | 1 | 2 | |||
Preliminary Design Review - Group 2 & 3 Various Vehicles | Aug 11 | N/A | Sep 11 | 0 |
| ||
Detailed Design | Group 1 - Various Vehicles | Dec 10 | N/A | Jan 11 | 1 | 3 | |
Dec 10 | N/A | Jan 11 | 1 |
| |||
Dec 11 | N/A | Dec 11 | 0 |
| |||
Group 2 & 3 - Various Vehicles | Nov 11 | N/A | Dec 11 | 1 |
| ||
Notes | |||||||
1 | The System Design Review was achieved when all major action items resulting from the review were completed, and the progress certificate was issued. | ||||||
2 | System Preliminary Design Review was delayed to align with the conduct of the Dismounted and Group 1 reviews. | ||||||
3 | The Detailed Design Reviews were aligned to incorporate the conduct of dismounted human factorstrials and the dismounted design review and input from vehicle Original Equipment Manufacturers relating to Detailed Design Review Group 1. Delay is also attributable to the finalisation of a contract change to the design schedule. | ||||||