Test and Evaluation | Major System / Platform Variant | Original Planned | Current Planned | Achieved /Forecast | Variance (Months) | Notes | |
System Integration | VMF Conformance to standard testing | Jun 11 | N/A | Jun 11 | 0 | 1 | |
Communications | May -Oct 10 | N/A | Jul - Oct 10 | 0 |
| ||
Acceptance Test and Evaluation - Command Post - Man Portable (CP-MP) | Apr -Jun 11 | N/A | May - Jun 11 | 1 | 2 | ||
Acceptance Test and Evaluation -Group 1 Various Vehicles | Apr -Jun 11 | N/A | May - Jul 11 | 1 | 2 | ||
| Acceptance Test and Evaluation -System | Jun -Aug 11 | N/A | Jun - Aug 11 | 0 |
| |
| Acceptance Test and Evaluation -Group 2 Various Vehicles | Feb 12 | N/A | Feb 12 | 0 |
| |
Notes | |||||||
1 | The first tranche of testing is complete, further testing is planned for the next 12 months | ||||||
2 | Delays in formal testing are attributable to: delays in the receipt of some equipment, and the receipt and agreement of final test procedures. In addition, availability of specialist test chambers remain a key constraint. | ||||||