Maturity Score | Attributes |
| |||||||
Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | Total | ||
Project Stage | Benchmark | 7 | 7 | 7 | 8 | 7 | 7 | 7 | 50 |
Critical Design Review | Project Status | 7 | 7 | 8 | 7 | 7 | 7 | 7 | 50 |
Explanation | • Technical Understanding: Despite the successful exit from the support system detailed design review, several important elements of the logistic support system such as the Training Management Plan and the Training Equipment and Materials List are yet to be approved. Once these are in place, the necessary logistic data and arrangements in support of the capability are likely to be in place. • Requirement: Definition of the system and sub-system design and the required system integration is very nearly complete. There are still challenges in execution of the program within the aggressive schedule, but there is a high confidence that the requirements will be satisfied by the system when it is delivered. | ||||||||
| |||||||||
2010-11 DMO MPRStatus -- - - | |||||||||