Data Element No / Heading | Data | Definition/ Description |
Section 1.2 - Current Status | Cost Performance | At a strategic level, state the project's current progress against its approved and in-year budgets, and provide a succinct explanation of causes for variations. This section must be consistent with the data in Section 2 Financial Performance. |
Schedule Performance | At a strategic level, briefly describe key schedule milestones achieved so far and issues facing the project in achieving future milestones. Milestone achievements or non-achievements in the current year should also be explained. This section must be consistent with what is stated in Section 3 Schedule Performance. | |
Materiel Capability Performance | At a strategic level, detail how the systems under acquisition are performing. Detailed technical performance of systems is to be avoided and classified information is not to be disclosed in this section. |