Section 1.2 - Current Status

Data Element No / Heading

Data

Definition/ Description

Section 1.2 - Current Status

Cost Performance

At a strategic level, state the project's current progress against its approved and in-year budgets, and provide a succinct explanation of causes for variations.

This section must be consistent with the data in Section 2 Financial Performance.

Schedule Performance

At a strategic level, briefly describe key schedule milestones achieved so far and issues facing the project in achieving future milestones. Milestone achievements or non-achievements in the current year should also be explained.

This section must be consistent with what is stated in Section 3 Schedule Performance.

Materiel Capability Performance

At a strategic level, detail how the systems under acquisition are performing. Detailed technical performance of systems is to be avoided and classified information is not to be disclosed in this section.