Section 3.1 - Design Review Progress

Data Element No / Heading

Data

Definition/ Description

SECTION 3 - SCHEDULE PERFORMANCE

Section 3.1 - Design Review Progress

Review

The events to be included are shown below as they are applicable to the project:

•  System Requirements Review

•  Preliminary Design Review

•  Critical Design Review.

Major System/ Platform Variant

State the major system that the Design review refers to.

Original Planned

The originally planned achievement dates for the events per the contract at execution.

Current Planned

Replanned dates as evidenced by a contract amendment.

Achieved/ Forecast

Achieved: The date the event was achieved.
Forecast: The expected date for achievement.

Variance (months)

The difference between 'Original Planned' and 'Achieved / Forecast'.

Notes

A top level description of the reasons for the variance to Achieved / Forecast dates, and any additional background information as required.