Data Element No / Heading | Data | Definition/ Description |
SECTION 3 - SCHEDULE PERFORMANCE | ||
Section 3.1 - Design Review Progress | Review | The events to be included are shown below as they are applicable to the project: • System Requirements Review • Preliminary Design Review • Critical Design Review. |
Major System/ Platform Variant | State the major system that the Design review refers to. | |
Original Planned | The originally planned achievement dates for the events per the contract at execution. | |
Current Planned | Replanned dates as evidenced by a contract amendment. | |
Achieved/ Forecast | Achieved: The date the event was achieved. | |
Variance (months) | The difference between 'Original Planned' and 'Achieved / Forecast'. | |
Notes | A top level description of the reasons for the variance to Achieved / Forecast dates, and any additional background information as required. | |