Data Element No / Heading | Data | Definition/ Description |
Section 3.2 - Contractor Test and Evaluation Progress | Test and Evaluation | The events to be included are shown below as they are applicable to the project: • System Integration • Acceptance. |
Major System/ Platform Variant | State the major system that the Test and Evaluation event refers to. If there are significant variants for the major systems then state what they are. | |
Original Planned | The originally planned achievement dates for the events per the contract at execution. | |
Current Planned | Replanned dates as evidenced by a contract amendment. | |
Achieved/ Forecast | Achieved: The date the event was achieved. | |
Variance (months) | The difference between 'Original Planned' and 'Achieved / Forecast'. | |
Notes | A top level description of the reasons for the variance to Achieved / Forecast dates, and any additional background information as required. |