Section 3.3 - Progress Toward Materiel Release and Operational Capability Milestones

Data Element No / Heading

Data

Definition/ Description

Section 3.3 - Progress Toward Materiel Release and Operational Capability Milestones

Item

Represented at a whole of capability level, unless key milestones are broken out under individual Mission or Support Systems.

Original Planned

The original date on which the Mission or Support System element was scheduled to achieve the key milestone.

Current Planned

Replanned dates as evidenced by a contract amendment.

Achieved/ Forecast

Achieved: The date the event was achieved.
Forecast: The expected date for achievement.

Variance (months)

The difference between original and achieved.

Variance Explanations

A top level description of the reasons for the variance to 'Achieved / Forecast' dates.

Schedule Status Bar Graph

 

DMO MPR Management will input the projects existing detail on: 2nd Pass Approval, IMR, IOC, FMR and FOC into the Bar Graph formula and produce the Graph.